After the needs analysis, the consultation and the decision, the practical work begins. This article sets out the steps from placing the order to the go-live — and what follows after that. Which routes into an implementation exist and how they differ is set out under LIMS implementation in test labs.  

From the order to the first working version

First the laboratory's IT infrastructure is analysed, so that the laboratory management system fits into the existing systems as well as possible. After that, the order in which the individual functional areas are built is agreed.

From then on there is a prototype every four weeks. Real data can be used with the very first one, and that data is retained throughout the whole prototype phase. The functions mature from round to round and the scope grows — and with it the experience of the people who will later use the system.

How long an implementation takes

Development usually takes between nine months and one and a half years, depending on the scope of the project.

Once the final prototype has been approved, training for administrators and users follows, together with a roll-out plan. At the end of it comes the go-live. What happens after that is for the laboratory to decide.

Communication decides the project

Throughout the project the communication strategy is the most important single element. Introducing a LIMS changes established working routines — and the complexity is regularly underestimated.

The most important piece of advice from project practice is therefore to take your own people with you. Transparent communication prevents misunderstandings and false expectations before they arise.

That includes a project manager in the laboratory who carries the responsibility and for whom the necessary time is actually set aside. The works council and the data protection officer belong in the project early, not shortly before the go-live.

And the users who will work with the system every day should be able to work with it as early as possible. That is the only way errors are found early — and the decisive observations regularly come from day-to-day laboratory work, not from the specification.

Who belongs in the project team

Two groups are needed for a project to run smoothly.

The Steering Committee brings together dacore's project management and the decision-makers in the laboratory: management, laboratory management and those responsible for IT. Once a month the key points of the project are discussed there.

The working team consists of the project managers from both sides, one member of staff from each of the specialist groups whose requirements are covered and, where several sites are involved, the people responsible for those sites.

Project management on the laboratory's side is a central and time-consuming task. Experience shows that it does not work if a laboratory manager is expected to take it on alongside their normal duties.

During the implementation phase the working team gets to know the system well enough to run the user training itself in many cases. Beforehand, those involved are trained as administrators over two days, either at dacore or on site in the laboratory.

Why detours are part of the project

Introducing a system that covers the most varied departments of a technical testing laboratory cannot run entirely smoothly.

In the course of a project it regularly turns out that individual things do not work — because users point out, for instance, that their workflow has not been mapped correctly. That is normal: no project team can know every special case in advance.

An example from practice: at one customer, test items were to be scanned straight off the rack from a forklift truck. On site it turned out that the barcodes could not be read reliably from that distance. The entire process had to be rethought and reprogrammed.

Loops like that cost time, and occasionally a fully developed module is discarded. That is exactly what contributes to acceptance in the end: staff see that their observations reach the system.

These points are resolved over the course of the prototype phases, until the system holds up in daily work.

After the go-live

The phases from demo to go-live, with duration and costs, are set out under LIMS implementation in test labs.